Bill of Quantities Format for Fire-fighting Works

  • Excel (.xlsx)
  • 5 sheets
  • Free
  • Updated

Or download the empty Excel template

What is a fire-fighting BOQ?

A fire-fighting BOQ is a bill of quantities for a building's fire-fighting system: pumps and the pump room, piping, valves, hydrants and hose reels, sprinklers, fire extinguishers, detection and alarm, and testing. Each item has a unit, a quantity and a rate for supply, installation, testing and commissioning.

What is in the fire-fighting BOQ workbook?

  • Project Details — name of work, parties, drawing and tender references, the source of your rates, and the add-on percentages.
  • BOQ — suggested items in eight sections — pumps and pump room, piping, valves, hydrant and hose system, sprinkler system, fire extinguishers, detection and alarm, testing and documentation — with blank rows for your own.
  • Abstract — every section's total, the add-ons and the total estimated cost, with a count of items still missing a rate.
  • Filled Sample — a worked example with illustrative quantities and rates.

How does the fire-fighting BOQ sheet calculate?

  • Amount = ROUND(quantity × rate, 2). An item with a quantity and no rate shows RATE MISSING and adds nothing, so a missing rate is never mistaken for a nil one.
  • Section sub-total = the sum of its amounts, with a count of items still without a rate.
  • Abstract: cost of works = the sum of the sections; contingencies and contractor's profit and overheads are each a percentage of the cost of works; GST is a percentage of the total before GST. Every percentage starts at 0.

Worked example from the sample sheet: a hydrant and hose-reel system with sixteen extinguishers for a small office building comes to Rs. 10,60,200 before add-ons. The main pump, jockey pump and control panel are Rs. 5,35,000 of it, about half.

How do you use the fire-fighting BOQ template?

  1. Fill in Project Details, including where your rates come from and any add-on percentages.
  2. On the BOQ sheet, overwrite or delete the suggested items and add your own in the blank rows of each section.
  3. Enter the measured quantity and the rate for each item. An item with a quantity and no rate shows RATE MISSING and is left out of the totals.
  4. Check the Abstract: section totals, add-ons, the total, and the count of items still without a rate.

What should you check before relying on the fire-fighting BOQ?

  • No rates are supplied. Price from current quotations or the schedule of rates your contract names, and record the source; the rates on the Filled Sample are illustrative only.
  • This BOQ prices a design; it is not a design. Pump capacities, pipe sizes and the number and spacing of hydrants, sprinklers and extinguishers come from the fire-fighting design approved under the National Building Code and by the local fire authority.
  • Rates are for supply, installation, testing and commissioning. If your tender splits supply and installation, add a column or say so in each description.

Which BOQ template do I need?

Your jobUse this template
Government, PWD or public-sector tender priced from a schedule of rates BOQ Format in Excel
New house or builder floor, private work — turnkey or labour contract House Construction BOQ Format in Excel (Private Work)
Renovation or repair mixing several trades: dismantling, waterproofing, tiling, painting, fabrication, POP Renovation & Trade Works BOQ Format in Excel
Only waterproofing: terrace, toilets, basement or water tank Waterproofing BOQ Format in Excel
Only flooring and tiling: tiles, stone, skirting and dado Flooring & Tiling BOQ Format in Excel
Only painting: interior, exterior, steel and woodwork Painting BOQ Format in Excel
Only the boundary wall and gate Boundary Wall BOQ Format in Excel
Office, shop or home interior fit-out Interior Work BOQ Format in Excel
Only plumbing and sanitary work Plumbing & Sanitary BOQ Format in Excel
Only internal electrical work Electrical BOQ Format in Excel
A building's fire-fighting system: pumps, hydrants, sprinklers, extinguishers Fire Fighting BOQ Format in Excel (this page)
A road, pavement or internal road Road Work BOQ Format in Excel
Adding several BOQs up into one project total Abstract of Cost Format in Excel

What does each column mean?

ColumnWhat goes in it
S. No.Section letter and item number, for example B.2.
Description of ItemWhat is to be done, in tender style. Write in the product, thickness, grade or number of coats your specification calls for.
UnitThe unit of measurement: sqm, rmt, cum, nos, set or job.
QuantityThe measured quantity in that unit.
Rate (Rs.)Your rate per unit, from quotations, a schedule of rates or your own analysis. None is supplied.
Amount (Rs.)Auto-calculated. Quantity × rate, rounded to two decimals.
CheckAuto-calculated. RATE MISSING or QTY MISSING when only one of the two is entered.

Everything in this band is priced on a bill of quantities. The BOQ format in Excel is that bill — pre-sectioned by trade, with an abstract that totals it — and every rate you settle here is applied against its measured quantities.

Get the quantities from your drawings

A template gives you the structure. The measuring — scaling every quantity off the drawing set — is still three to seven days of work. Upload your architectural and structural PDFs and InstaBOQ reads the drawings, extracts the quantities, and fills this same structure.

Questions

What does a fire-fighting BOQ include?

The fire pumps and their controls, the piping and valves, internal and external hydrants, hose reels and hoses, sprinklers, fire extinguishers, fire detection and alarm where it is in the same package, and the testing, commissioning and as-built drawings.

Who decides the pump capacity and the number of hydrants?

The fire-fighting design, prepared to the National Building Code and the requirements of the local fire authority for the building's use and height. The BOQ only prices what the approved design shows.

Are fire-fighting rates for supply only or supply and installation?

This template assumes one rate for supply, installation, testing and commissioning. Many tenders ask for separate supply and installation rates; if yours does, add a column or state it in the description.

How is fire-fighting pipe measured?

In running metres along the run, by diameter. The suggested items include fittings, supports and painting in the pipe rate; if your tender measures fittings separately, add them as their own items.

Is testing and commissioning priced separately?

Yes, as a job item covering hydrostatic testing, commissioning of the whole system, as-built drawings and handing over, so it is not lost inside the equipment rates.