Site Indent Format for Material and Labour

Quantity to procure from requirement less stock, plus a separate trade-wise labour indent sheet.

  • Excel (.xlsx)
  • 5 sheets
  • Free
  • Updated

What is in the file

  • Instructions
  • Project Details
  • Material Indent
  • Labour Indent
  • Filled Sample

What is a site indent?

An indent is the formal request from site to the purchase or HR function for material or manpower. Raising it in writing, against a stated item of work and a required-by date, is what makes a shortage traceable to a decision rather than to nobody.

What is in the site indent workbook?

  • Project Details — indent number, date, site and required-by date.
  • Material Indent — material-wise requirement, stock in hand, and quantity to procure.
  • Labour Indent — trade-wise manpower requirement with the period needed.
  • Filled Sample — a worked example of a material and labour indent raised mid-project for a first floor slab.

How does the site indent sheet calculate?

  • Quantity to procure = quantity required − stock in hand, and never less than zero, so surplus stock never turns into a negative order.
  • Total manpower required on the labour indent is the sum of the numbers required across trades.

Worked example from the sample sheet: 600 bags of cement are required for the first-floor slab and columns, with 240 bags in hand, so the indent asks for 360 bags.

How do you use the site indent template?

  1. Fill in the indent number, date and required-by date on Project Details.
  2. On Material Indent, enter each material with its approved make or specification, the quantity required, and the stock already in hand. The quantity to procure calculates itself.
  3. State the item of work each material is for. This is what allows the indent to be checked against the BOQ later.
  4. On Labour Indent, enter the trades required, the numbers, and the period they are needed for.
  5. Route both sheets for approval before sending to purchase. An unapproved indent is the usual reason a delivery is disputed.

What should you check before relying on the site indent?

  • Indent against the work programme and the lead time of the material, not against the day you run out. Cement, steel and made-to-order items all have lead times.
  • The specification column is not optional. Most material disputes on site trace back to an indent that named a material but not a make or grade.
  • Check stock in hand from the store register before indenting. This template calculates whatever you enter — it cannot know your real stock.
  • Keep indents in a numbered series and file the approved copy. It is the document that supports a claim for idling if material arrives late.
  • Rates are not supplied with this template. Enter rates from your own schedule of rates or market quotations; any figures on the sample sheet are illustrative only and must not be used for real estimating or billing.

What does each column mean?

ColumnWhat goes in it
S. No.Row number. Keep indents in a numbered series and file the approved copy.
MaterialThe material being requisitioned.
Specification / Approved MakeGrade, make or specification. Not optional — most material disputes trace back to an indent that named a material but not a make.
UnitThe unit the material is ordered in.
Quantity RequiredThe quantity the work needs.
Stock in HandQuantity already in store, checked against the store register.
Quantity to ProcureAuto-calculated. Quantity required minus stock in hand.
Required by (Date)The date the material is needed — set against the work programme and the material's lead time, not the day you run out.
Item of Work / LocationThe item of work the material is for, so the indent can be checked against the BOQ later.
RemarksAnything the purchase function needs — part deliveries acceptable, access constraints, and so on.

An indent is only closed when the material arrives. Book each delivery against it in the material receipt (GRN) and stock register, which also gives you the stock-in-hand figure the next indent starts from.

Get the quantities from your drawings

These records only mean something against an accurate bill of the work. Upload your drawings and InstaBOQ produces the measured, itemised BOQ your consumption norms and reconciliations are checked against.

Questions

What is a material indent in construction?

A site indent is the site's formal request for material or labour: what is needed, how much, by when, and for which item of work. It is raised against the work programme and checked against stock in hand before anything is ordered.

What is the difference between an indent and a purchase order?

An indent is an internal request from site. A purchase order is issued by the purchase or head office to a supplier once the indent is approved.

Why must an indent state the specification or approved make?

An indent that names only the material invites the cheapest substitute. Stating the grade, size and approved make means what arrives is what the drawings and contract require.

How is the quantity to procure calculated?

Quantity required minus stock in hand, never less than zero. Take the stock-in-hand figure from the store register, not from memory.

Why raise a labour indent separately?

Manpower has to be arranged against the programme ahead of time. A labour indent by trade, with the period and the work it is for, lets the labour contractor plan instead of reacting to yesterday's shortfall.