Deviation / Variation Statement Format

Excess and saving item by item at agreement rates, a separate extra-items part, and a linked summary.

  • Excel (.xlsx)
  • 5 sheets
  • Free
  • Updated

What is in the file

  • Instructions
  • Project Details
  • Deviation Statement
  • Filled Sample
  • Summary

What is a deviation statement?

A Deviation Statement records the difference between the quantities in the agreement and the quantities actually executed or anticipated, item by item, and lists any extra items outside the original scope. It is the document on which additional payment or revised sanction is approved.

What is in the deviation statement workbook?

  • Project Details — project particulars and the original agreement value.
  • Deviation Statement — Part I, agreement items with excess and saving; Part II, extra items.
  • Summary — net deviation, revised value and deviation percentage, all linked.
  • Filled Sample — a worked example with ten agreement items and three extra items.

How does the deviation statement sheet calculate?

  • Agreement amount = agreement rate × agreement quantity; executed amount = agreement rate × executed or anticipated quantity.
  • Excess = executed − agreement quantity, when more was executed; saving = agreement − executed quantity, when less was. Each is valued at the agreement rate, and an item can show one or the other, never both.
  • Extra items (Part II) are not in the agreement, so their whole executed quantity and amount count as excess.
  • Net deviation = total excess − total saving; revised value = agreement value + net deviation; and the net deviation is also shown as a percentage of the agreement value.

Worked example from the sample sheet (illustrative rates): excavation agreed at 420 cum but executed at 486 cum is an excess of 66 cum × ₹310 = ₹20,460. PCC agreed at 46 cum but executed at 44.5 cum is a saving of 1.5 cum × ₹4,820 = ₹7,230.

How do you use the deviation statement template?

  1. Enter the project particulars and the original agreement value on Project Details.
  2. In Part I of the Deviation Statement sheet, list every agreement item with its rate, agreement quantity, and the quantity executed or anticipated.
  3. Excess and saving are worked out automatically at agreement rates. An item shows in one column or the other, never both.
  4. In Part II, list extra items that are not in the agreement at all, with the rate approved for each.
  5. Check the Summary sheet — it is already linked — and record the reasons for deviation and the sanction reference before routing for signature.

What should you check before relying on the deviation statement?

  • Extra-item rates must be derived and approved before the work is done. A rate settled after execution invites dispute and is often disallowed.
  • Show anticipated quantities, not just executed ones, if the statement is put up for sanction mid-contract. Label clearly which is which.
  • Deviation limits, and the authority competent to sanction them, are set by your agreement or departmental code. Confirm both before relying on this statement.
  • Saving on one item does not automatically fund excess on another unless your contract permits it.
  • Rates are not supplied with this template. Enter rates from your own schedule of rates or market quotations; any figures on the sample sheet are illustrative only and must not be used for real estimating or billing.

What does each column mean?

ColumnWhat goes in it
S. No.Item number. Part I lists agreement items; Part II lists extra items outside the original scope.
Description of ItemThe item as worded in the agreement (Part I), or the approved extra item (Part II).
UnitAs in the agreement.
Rate (Rs.)The agreement rate. Both excess and saving are valued at this rate.
Agreement QtyThe quantity provided in the agreement.
Agreement Amount (Rs.)Auto-calculated. Agreement quantity x rate.
Executed / Anticipated QtyThe quantity actually executed, or anticipated if the statement is put up for sanction mid-contract. Label which.
Executed Amount (Rs.)Auto-calculated. Executed quantity x rate.
Excess QtyAuto-calculated. Quantity above the agreement, if any.
Excess Amount (Rs.)Auto-calculated. Excess quantity x rate.
Saving QtyAuto-calculated. Quantity below the agreement, if any. An item shows in excess or in saving, never both.
Saving Amount (Rs.)Auto-calculated. Saving quantity x rate.

A bill for payment is only as sound as the take-off behind it. The detailed measurement sheet format is where the quantities on this bill are measured and abstracted, item by item.

The quantities actually executed are the ones you bill. Carry them into the RA bill format in Excel.

Get the quantities from your drawings

The arithmetic in this workbook is the quick part. Reading dimensions off a full drawing set, item by item, is what takes days. Upload your drawings and InstaBOQ measures them for you and abstracts the quantities into this same structure.

Questions

What is a deviation statement in construction?

A deviation statement compares the quantities in the agreement with the quantities executed or expected to be executed, item by item, and values the difference at agreement rates. It is prepared to get variations sanctioned, and before the final bill.

What is the difference between excess, saving and an extra item?

An excess is more of an agreement item than the agreement provided; a saving is less. An extra item is work not in the agreement at all, so its whole quantity counts as deviation and its rate has to be settled separately.

What is the deviation limit in a construction contract?

Most contracts cap how far quantities may vary before higher sanction is needed or rates are revised. The limit and what happens beyond it are set by your agreement, so check it before executing work that crosses it.

How are rates for extra items decided?

By the method your contract sets out, commonly from a schedule of rates or by an analysis of rates for the new item.

How is the revised value of the work calculated?

Revised value = original agreement value + total excess - total saving. The sheet also shows the net deviation as a percentage of the agreement value.