Running Account (RA) Bill Format in Excel

  • Excel (.xlsx)
  • 6 sheets
  • Free
  • Updated

Or download the empty Excel template

What is a running account (RA) bill?

A Running Account Bill is the periodic bill a contractor raises for work completed to date on a running contract. It shows cumulative quantities up to date, subtracts what was already paid in earlier bills, and arrives at the amount due for the current period after statutory and contractual deductions.

Labour-only contract? Use the labour bill format.

What is in the RA bill workbook?

  • Contract Details — project, agreement and bill particulars, Running or Final bill, the GST rate and every deduction percentage used elsewhere in the workbook.
  • Previous Bills — what each earlier bill billed, held back as retention and paid, for the totals to date.
  • RA Bill Working — item-wise quantities and value, with the Measurement Book page for each item. The present-bill columns are calculated.
  • Deductions & Summary — pulls the totals and percentages from the sheets above and works out GST, every deduction, retention released, the net amount payable and the totals to date.
  • Filled Sample — a worked example for an RCC framed building, RA Bill No. 3, with two previous bills.

How does the RA bill sheet calculate?

  • Quantity for present bill = quantity up to date − quantity up to previous bill.
  • Amount up to date and amount up to previous bill = the respective quantity × agreement rate. The value of work done in this bill is the difference between them.
  • Gross amount of this bill = value of work done in this bill + any escalation or other addition payable.
  • GST, where the contractor charges it, is added on the gross amount of this bill.
  • Every deduction — security deposit, income-tax TDS, GST TDS, labour welfare cess, advance recoveries, water and electricity — is the gross amount of this bill × its percentage from the Contract Details sheet. Earlier bills' work is never deducted twice.
  • Net amount payable = gross amount of this bill + GST − total deductions + any retention released.
  • Retention held = retention in previous bills + retention on this bill − retention released. A final bill releases retention only when you enter an amount, because it is often held until the defect liability period ends.

Worked example from the sample RA Bill No. 3 (illustrative rates): work done up to date is ₹59,70,250 and up to the previous bill ₹41,46,950, so this bill's value is ₹18,23,300. Security deposit at 5% (₹91,165), income-tax TDS at 2% (₹36,466) and labour cess at 1% (₹18,233) leave a net amount payable of ₹16,77,436.

How do you use the RA bill template?

  1. Open the Contract Details sheet and fill in the project, agreement and bill particulars. Choose Running or Final, enter the GST rate if the contractor charges GST, and set the deduction percentages to match your agreement.
  2. On Previous Bills, add a row for each bill already paid. For RA Bill No. 1 leave it empty.
  3. Go to RA Bill Working. Enter each item, its unit, agreement quantity and rate.
  4. In "Qty up to Previous Bill", enter the cumulative quantity certified in your last RA bill. For RA Bill No. 1 this column stays zero.
  5. In "Qty up to Date", enter the total cumulative quantity executed as measured in the Measurement Book. The present-bill quantity and all amounts calculate themselves.
  6. Open Deductions & Summary. It is already linked — check the figures and enter any escalation or other recovery.
  7. Print or export to PDF and route for signature. Carry the "Qty up to Date" column forward into the next bill.

What should you check before relying on the RA bill?

  • This is a general-purpose format. Government departments and PSUs each prescribe their own bill proforma — check which applies to your contract.
  • Quantities entered here must match the Measurement Book. The MB is the primary record; this bill is a summary of it.
  • Deduction percentages are set on the Contract Details sheet only. The summary sheet reads them from there, so change them in one place.
  • Add rows inside the existing table rather than below the total row, so the total keeps picking them up.
  • Rates are not supplied with this template. Enter rates from your own schedule of rates or market quotations; any figures on the sample sheet are illustrative only and must not be used for real estimating or billing.

What does each column mean?

ColumnWhat goes in it
S. No.Item number, matching the agreement schedule.
Description of ItemThe item as worded in the agreement.
UnitAs in the agreement.
Contract QtyThe quantity in the contract or work order, so work beyond it is flagged.
Rate (Rs.)The agreement rate for the item.
Qty up to Previous BillCumulative quantity certified in your last RA bill. Zero for RA Bill No. 1.
Qty up to DateTotal cumulative quantity executed to date, as measured in the Measurement Book.
Qty for Present BillAuto-calculated. Quantity up to date minus quantity up to the previous bill.
Amount up to Previous Bill (Rs.)Auto-calculated. Previous cumulative quantity x rate.
Amount up to Date (Rs.)Auto-calculated. Quantity up to date x rate.
Amount for Present Bill (Rs.)Auto-calculated. The value of work done this period, before deductions.
MB No. / PageWhere the measurement for the item is recorded in the Measurement Book.
CheckNOT PRICED when a quantity has no rate (left out of the totals, never counted as zero), OVER CONTRACT QTY, LESS THAN PREVIOUS.

A bill for payment is only as sound as the take-off behind it. The detailed measurement sheet format is where the quantities on this bill are measured and abstracted, item by item.

Where the quantities executed depart from the agreement, record the difference in the deviation statement format.

Get the quantities from your drawings

The arithmetic in this workbook is the quick part. Reading dimensions off a full drawing set, item by item, is what takes days. Upload your drawings and InstaBOQ measures them for you and abstracts the quantities into this same structure.

Questions

What is an RA bill in construction?

A Running Account (RA) bill is an interim bill a contractor raises for work done to date on a running contract. Each bill measures cumulative quantities, subtracts what was paid in earlier bills, and arrives at the amount due for the period after deductions. The final bill closes the account at completion.

Why does an RA bill use cumulative quantities?

Measuring quantities up to date each time means any error in an earlier bill is corrected in the next one. The quantity for the present bill is simply the quantity up to date minus the quantity up to the previous bill.

Are RA bill deductions calculated on this bill or on the value up to date?

On this bill's gross amount. Deducting on the cumulative value up to date would deduct again on work already deducted in earlier bills, unless the deductions made in previous bills are subtracted. This template applies each percentage to the gross amount of the present bill.

What deductions are made from an RA bill?

Typically security deposit or retention, income-tax TDS, GST TDS where applicable, labour welfare cess, recovery of mobilisation and secured advances, and water and electricity charges. The percentages come from your agreement and current law; the template's defaults are placeholders.

Is GST deducted in an RA bill?

No, it is added. A GST-registered contractor charges GST on the gross amount of the bill, and the workbook adds it on the Deductions & Summary sheet. Retention, TDS and the other deductions are worked out on the amount before GST. GST TDS, where applicable, is a separate deduction.

What is a final bill, and is retention released with it?

The final bill is the last bill on a contract: it bills the remaining work and closes the account. Retention is often not returned with it — many contracts hold it until the defect liability period ends. Set Bill Type to Final, and enter a release amount only when your contract says it is due.

Does the RA bill workbook keep track of previous payments?

Yes. The Previous Bills sheet lists what each earlier bill billed, held back as retention and paid, and the summary shows the totals to date and the retention still held.

Next in your work

Work done this bill, GST, retention, TDS and recoveries, net payable, previous bills and the final bill. Carries quantities forward to the next bill and downloads a filled RA bill.