Lesson 3 of 6

Turn spacing into a steel quantity

Count stirrups over a clear span, then calculate total length, unit weight and kilograms of steel.

  1. 1Turn spacing into a count
  2. 2Repeat the whole member
  3. 3Convert total length into steel weight
  4. 4Your turn
Drawing deskDimensions · mm
4,000mm clear span41 bars · 100mm spacing
100mm centres
Drawing deskDimensions · mm
4,000mm clear span27 bars · 150mm spacing
150mm centres
Drawing deskDimensions · mm
4,000mm clear span21 bars · 200mm spacing
200mm centres

Learn · Part 1

Turn spacing into a count

Choose a spacing. Closer centres mean more stirrups.

100mm centres

41 bars per beam

floor(4000 / 100) + 1 = 41. This course places the first bar at the start of the clear span; the drawing governs actual offsets and zones.

Total bars
123
Steel
59.28kg

150mm centres

27 bars per beam

floor(4000 / 150) + 1 = 27. This course places the first bar at the start of the clear span; the drawing governs actual offsets and zones.

Total bars
81
Steel
39.04kg

200mm centres

21 bars per beam

floor(4000 / 200) + 1 = 21. This course places the first bar at the start of the clear span; the drawing governs actual offsets and zones.

Total bars
63
Steel
30.36kg
Drawing deskDimensions · mm
4,000mm clear span27 bars · 150mm spacing
1 beam
Drawing deskDimensions · mm
4,000mm clear span27 bars · 150mm spacing
3 beams

Learn · Part 2

Repeat the whole member

Reset to 150mm centres. Keep bars per member separate from the number of members.

1 beam

27 bars total

27 bars × 1 beams = 27 bars. 27 × 1220 / 1000 = 32.94m.

Total length
32.94m

3 beams

81 bars total

27 bars × 3 beams = 81 bars. 81 × 1220 / 1000 = 98.82m.

Total length
98.82m
Drawing deskDimensions · mm
One cut bar · 1,220mm
Unit weight
Drawing deskDimensions · mm
4,000mm clear span27 bars · 150mm spacing
All stirrups

Learn · Part 3

Convert total length into steel weight

Use the same 8mm bar and all three beams.

Unit weight

0.4 kg per metre

Nominal unit weight = d² / 162. Keep the unrounded value in the calculation.

All stirrups

39.04 kg

98.82m × the unrounded unit weight = 39.04kg. This excludes main bars and wastage.

Apply what you learned

Your turn.

Change spacing to 100mm over one 4,000mm clear span. How many stirrups?

See the worked solution

floor(4000 / 100) + 1 = 41 bars.

Answer: 41 bars.

Lesson notes & reference

Worked exampleAt 150mm centres, there are 27 stirrups per beam and 81 across 3 beams.

Your starting point

Carry forward the 1,220mm cutting length from Lesson 2 and apply it to three 4,000mm beam spans.

Read the complete lesson

1. Turn spacing into a count

Choose a spacing. Closer centres mean more stirrups.

100mm centres · 41 bars per beam

floor(4000 / 100) + 1 = 41. This course places the first bar at the start of the clear span; the drawing governs actual offsets and zones.

Total bars
123
Steel
59.28kg

150mm centres · 27 bars per beam

floor(4000 / 150) + 1 = 27. This course places the first bar at the start of the clear span; the drawing governs actual offsets and zones.

Total bars
81
Steel
39.04kg

200mm centres · 21 bars per beam

floor(4000 / 200) + 1 = 21. This course places the first bar at the start of the clear span; the drawing governs actual offsets and zones.

Total bars
63
Steel
30.36kg

2. Repeat the whole member

Reset to 150mm centres. Keep bars per member separate from the number of members.

1 beam · 27 bars total

27 bars × 1 beams = 27 bars. 27 × 1220 / 1000 = 32.94m.

Total length
32.94m

3 beams · 81 bars total

27 bars × 3 beams = 81 bars. 81 × 1220 / 1000 = 98.82m.

Total length
98.82m

3. Convert total length into steel weight

Use the same 8mm bar and all three beams.

Unit weight · 0.4 kg per metre

Nominal unit weight = d² / 162. Keep the unrounded value in the calculation.

All stirrups · 39.04 kg

98.82m × the unrounded unit weight = 39.04kg. This excludes main bars and wastage.

The schedule you’re building toward

The same worked example throughout the course: three identical beams, with three bottom and three top main bars in each.

230 × 450mm beams · 4,000mm clear span · 25mm cover
BarShapeDiaCutting lengthBars per memberTotal barsTotal lengthWeightNotes
S1 Stirrup · rectangular, 135° hooks 8mm 1220mm 27 81 98.82m 39.04kg Uniform centres; no zones
B1 Bottom main · straight 16mm 5500mm 3 9 49.50m 78.22kg Straight anchorage at both ends
T1 Top main · straight 16mm 5500mm 3 9 49.50m 78.22kg Straight anchorage at both ends

Total steel: 195.48kg. Worked quantities exclude wastage. Main bars assume straight anchorage fits each support; use the actual structural detail for a project.

A beam stirrup is one closed loop. What changes when a column needs cross-ties to restrain more bars?

Want the full detailed course?

This free course covers the fundamentals. Join the waitlist for the paid, detailed course — drawing-based worked examples, framing plans, and full projects.