Lesson 5 of 6

Make bars reach with development length and laps

Use grade-dependent development length, account for stock-length splices and include lap steel in the quantity.

  1. 1Development depends on the grades
  2. 2A splice consumes steel
  3. 3Check that every piece fits stock
  4. 4Your turn
Drawing deskDimensions · mm
Development into support · 752mm
M20 / Fe415
Drawing deskDimensions · mm
Development into support · 784mm
M25 / Fe500

Learn · Part 1

Development depends on the grades

Keep the bar diameter fixed and compare the two grade combinations.

M20 / Fe415

752 mm development

47d × 16mm = 752mm for this fully stressed deformed tension-bar example. Use the engineer’s specified anchorage for a real member.

M25 / Fe500

784 mm development

49d × 16mm = 784mm for this fully stressed deformed tension-bar example. Use the engineer’s specified anchorage for a real member.

Drawing deskDimensions · mm
Required reach · 15,000mm
Required reach
Drawing deskDimensions · mm
Reach · 15,000mmSteel including laps · 15,752mm
Include the lap

Learn · Part 2

A splice consumes steel

For the worked grades only, assume the drawing specifies a tension lap equal to Ld. That is an example input, not a universal lap rule.

Required reach

15,000 mm reach

Reach is the distance the joined bar must cover; it excludes the duplicated material within each overlap.

Include the lap

15,752 mm of steel

1 lap × 752mm = 752mm extra steel. Total steel is reach plus all overlaps.

Drawing deskDimensions · mm
Piece 1 · 12,000mmPiece 2 · 3,752mm
Piece breakdown

Learn · Part 3

Check that every piece fits stock

The stock limit applies to each fabricated piece.

Piece breakdown

2 pieces

12,000mm + 3,752mm; subtract the 752mm overlap to recover the required reach.

Apply what you learned

Your turn.

Using the 49d factor for M25 / Fe500, what is the development length of a 16mm bar?

See the worked solution

49 × 16 = 784mm.

Answer: 784.0 mm.

Lesson notes & reference

Worked exampleThe worked 16mm bar requires 752mm development for M20 / Fe415.

Your starting point

Main bars do not stop at a support face. Their cutting length must include anchorage, and long runs must include every lap.

Read the complete lesson

1. Development depends on the grades

Keep the bar diameter fixed and compare the two grade combinations.

M20 / Fe415 · 752 mm development

47d × 16mm = 752mm for this fully stressed deformed tension-bar example. Use the engineer’s specified anchorage for a real member.

M25 / Fe500 · 784 mm development

49d × 16mm = 784mm for this fully stressed deformed tension-bar example. Use the engineer’s specified anchorage for a real member.

2. A splice consumes steel

For the worked grades only, assume the drawing specifies a tension lap equal to Ld. That is an example input, not a universal lap rule.

Required reach · 15,000 mm reach

Reach is the distance the joined bar must cover; it excludes the duplicated material within each overlap.

Include the lap · 15,752 mm of steel

1 lap × 752mm = 752mm extra steel. Total steel is reach plus all overlaps.

3. Check that every piece fits stock

The stock limit applies to each fabricated piece.

Piece breakdown · 2 pieces

12,000mm + 3,752mm; subtract the 752mm overlap to recover the required reach.

The schedule you’re building toward

The same worked example throughout the course: three identical beams, with three bottom and three top main bars in each.

230 × 450mm beams · 4,000mm clear span · 25mm cover
BarShapeDiaCutting lengthBars per memberTotal barsTotal lengthWeightNotes
S1 Stirrup · rectangular, 135° hooks 8mm 1220mm 27 81 98.82m 39.04kg Uniform centres; no zones
B1 Bottom main · straight 16mm 5500mm 3 9 49.50m 78.22kg Straight anchorage at both ends
T1 Top main · straight 16mm 5500mm 3 9 49.50m 78.22kg Straight anchorage at both ends

Total steel: 195.48kg. Worked quantities exclude wastage. Main bars assume straight anchorage fits each support; use the actual structural detail for a project.

You have every calculation needed for the beam. Can you place the results into a schedule and catch an implausible total?

Want the full detailed course?

This free course covers the fundamentals. Join the waitlist for the paid, detailed course — drawing-based worked examples, framing plans, and full projects.