Pay application calculator
Progress billing in the layout US contractors know from the AIA G702 and G703: schedule of values, work this period, materials stored, retainage and the current payment due.
- Free
- Nothing is stored
- Up to 40 lines
Calculator
This is a filled example. Start a blank one.
Application summary
| 1. Original contract sum | $250,000.00 |
| 2. Net change by change orders | $4,500.00 |
| 3. Contract sum to date | $254,500.00 |
| 4. Total completed and stored to date | $145,500.00 |
| 5. Retainage: 10% of completed work $12,950.00, 10% of stored materials $1,600.00 | $14,550.00 |
| 6. Total earned less retainage | $130,950.00 |
| 7. Less previous certificates for payment | $78,300.00 |
| 8. Current payment due | $52,650.00 |
| 9. Balance to finish, including retainage | $123,550.00 |
Continuation sheet
| Item | Description | Scheduled value | Completed and stored to date | % | Balance to finish | Retainage |
|---|---|---|---|---|---|---|
| 01 | General conditions | $18,000.00 | $9,000.00 | 50.0% | $9,000.00 | $900.00 |
| 03 | Concrete: footings, stem wall, slab | $32,000.00 | $32,000.00 | 100.0% | $0.00 | $3,200.00 |
| 06 | Wood framing and sheathing | $48,500.00 | $48,500.00 | 100.0% | $0.00 | $4,850.00 |
| 07 | Roofing, siding and insulation | $36,000.00 | $18,500.00 | 51.4% | $17,500.00 | $1,850.00 |
| 08 | Doors and windows | $19,000.00 | $9,500.00 | 50.0% | $9,500.00 | $950.00 |
| 09 | Drywall, paint and flooring | $42,000.00 | $0.00 | 0.0% | $42,000.00 | $0.00 |
| 22 | Plumbing | $21,000.00 | $12,000.00 | 57.1% | $9,000.00 | $1,200.00 |
| 23 | Heating and cooling | $16,000.00 | $5,000.00 | 31.3% | $11,000.00 | $500.00 |
| 26 | Electrical | $22,000.00 | $11,000.00 | 50.0% | $11,000.00 | $1,100.00 |
| Total | $254,500.00 | $145,500.00 | $109,000.00 | $14,550.00 |
How to work out a pay application
- 1
Enter the contract
Original contract sum, net change orders and the retainage percentages.
- 2
Enter the schedule of values
For each line: scheduled value, work from previous applications, work this period and materials stored.
- 3
Enter previous certificates
What was certified for payment on earlier applications.
- 4
Read the payment due
The summary gives retainage, total earned, the current payment due and the balance to finish.
Frequently asked questions
What is a pay application?
The bill a contractor sends each month for the work done so far on a job. It lists each line of the schedule of values, the work completed before and this period, materials stored, the retainage held back, and the payment now due.
How is the current payment due worked out?
Total completed and stored to date, less retainage, is the total earned. Take away what was already certified on earlier applications, and what is left is the current payment due.
How is retainage calculated?
As a percentage of the work completed (previous plus this period) and, separately, of the materials stored. Both start at 10% here; change them to what your contract says.
Is this the AIA G702 form?
No. It follows the layout US contractors know from the AIA G702 and G703, and works out the same lines, but it is not the AIA document. Where your contract requires the AIA form, copy the figures into it.
What if a line has no scheduled value?
It is left out of the totals and named in the checks, never counted as $0.
Is anything I enter stored?
No. The figures are worked out when you press Calculate and are not saved.