Concrete Cube Test Register Format

Compressive strength from failure load and cube area, results grouped in sets of three with set averages.

  • Excel (.xlsx)
  • 4 sheets
  • Free
  • Updated

What is in the file

  • Instructions
  • Project Details
  • Cube Test Register
  • Filled Sample

What is a concrete cube test register?

A register of concrete cube samples cast on site and their compressive strength results at 7 and 28 days. It is a mandatory quality record on almost every reinforced concrete contract, and the evidence that the concrete supplied met the specified grade.

What is in the cube test register workbook?

  • Project Details — project particulars, laboratory, cube size and the derived cross-sectional area.
  • Cube Test Register — one row per cube, grouped in sets of three, with strengths and set averages calculated.
  • Filled Sample — four sets of illustrative results.

How does the cube test register sheet calculate?

  • Cross-sectional area = cube size × cube size; 150 mm cubes give 22,500 sq mm.
  • Compressive strength (N/sq mm) = failure load in kN × 1,000 ÷ cross-sectional area in sq mm, for both the 7-day and 28-day tests.
  • Set average = the average of the three 28-day strengths in the set.
  • The acceptance value for your grade is entered by you from IS 456:2000 Clause 16 and Table 11. The register records and compares; it does not apply the acceptance criteria for you.

Worked example from the sample sheet: a 150 mm cube failing at 640.2 kN has a strength of 640.2 × 1,000 ÷ 22,500 = 28.45 N/sq mm. With the other two cubes of the set at 29.27 and 28.84 N/sq mm, the set average is 28.85 N/sq mm.

How do you use the cube test register template?

  1. Confirm the cube size on Project Details. The cross-sectional area used in every strength calculation is worked out from it.
  2. Enter one row per cube, three rows per set. Record the cube ID, casting date, the member and location the sample came from, the grade and the slump measured.
  3. Enter the failure load in kN at 7 days and at 28 days. Compressive strength calculates automatically.
  4. Enter the acceptance value for your grade, taken from IS 456:2000 and your specification, against each set.
  5. The set average of the three 28-day results calculates itself and is shown once per set.

What should you check before relying on the cube test register?

  • This template calculates strength from load. It does not judge acceptance for you — IS 456 judges concrete on groups of consecutive results as well as on individual results, and the criteria depend on your grade and specification.
  • Record the exact member and location each sample came from. A result that cannot be traced back to a specific pour is of little use if a question arises later.
  • Slump should be the value measured at the point of placing, not at the batching plant.
  • Cube identification marks must be made before the cubes leave site and must match the laboratory's report.

What does each column mean?

ColumnWhat goes in it
Set No.The sample set. Three cubes per set; the set number repeats across its three rows.
Cube IDThe identification mark on the cube, made before it leaves site and matching the lab report.
Date of CastingThe day the cube was cast.
Member / LocationThe member and location the sample was taken from. A result that cannot be traced to a pour is of little use later.
GradeThe specified grade of the concrete — M20, M25, and so on.
Slump (mm)Slump measured at the point of placing, not at the batching plant.
Date of Test (7 d)The day the 7-day cube was tested.
7-day Load (kN)Failure load of the 7-day cube.
7-day Strength (N/sq mm)Auto-calculated. Load divided by the cube cross-sectional area.
Date of Test (28 d)The day the 28-day cube was tested.
28-day Load (kN)Failure load of the 28-day cube.
28-day Strength (N/sq mm)Auto-calculated. Load divided by the cube area.
Set Average (N/sq mm)Auto-calculated. Mean of the three 28-day results, shown once per set.
Acceptance Value (N/sq mm)The acceptance value for the grade, from IS 456 and your specification. This template calculates strength; it does not judge acceptance for you.

The quality record and the daily record are read together. Each sample logged here comes from a pour in the concrete pour register — the cube set IDs tie the two — and that day's daily progress report.

Get the quantities from your drawings

A progress record is measured against the estimate it reports against. Upload your drawings and InstaBOQ builds the measured BOQ — so "work executed today" can be tracked line by line against a real quantity.

Questions

How is the compressive strength of a concrete cube calculated?

Compressive strength = failure load / cross-sectional area. For a 150 mm cube the area is 22,500 sq mm, so a failure load of 640.2 kN gives 640.2 x 1,000 / 22,500 = 28.45 N/sq mm.

How many cubes make one sample?

Under IS 456:2000, the test result of a sample is the average strength of three specimens, and the individual variation should not be more than plus or minus 15% of the average; otherwise the test result of that sample is invalid.

How many samples should be taken from a pour?

IS 456:2000 Clause 15.2.2 sets the minimum: 1 sample for 1-5 cum of concrete, 2 for 6-15 cum, 3 for 16-30 cum, 4 for 31-50 cum, and for 51 cum and above, 4 plus one more for each additional 50 cum or part of it. At least one sample should be taken from each shift.

Why are cubes tested at 7 days and 28 days?

The specified grade of concrete is defined by its 28-day strength, so the 28-day result is the one acceptance is judged on. The 7-day result is an early indication that allows problems to be caught sooner.

What are the acceptance criteria for concrete cube test results?

They are given in IS 456:2000 Clause 16 and Table 11, and depend on the grade and on groups of consecutive results rather than on a single set. Enter the acceptance value for your grade in the register; the sheet records the results but does not apply the criteria for you.